What's going on right now?The USC Campus Center website lists the project as 14% complete. According to the Daily Trojan, the concrete slab for part of the basement has been poured, while another pour is scheduled next week. Meanwhile, the structural frame of the building is being constructed on the south side and should be completed by the middle of November. The structural frame on the north side should be completed by January 2009.
Want to continue to track progress?
There is one webcam on the Student Union building and another on the Bovard Administration building that look onto the construction site. These webcams can be viewed online with options for watching activity occurring in the past hour, or the past week.
Greeks getting involved?
This week is Greek Week at USC, and instead of having philanthropy events the various Greek councils are encouraging all Greeks to financially support the Campus Center. According to the Daily Trojan, the Greek councils are putting together packets to help the seniors in the Greek community start the process of giving back to USC, and in particular the Campus Center.
Have there been any complications thus far?
Executive Director of the Campus Center Patrick Bailey says the whole process has been pretty smooth thus far except for a few coordinating challenges. According to Bailey, there have been a couple times when the workers had to work odd hours so that campus activity was not disturbed, and Capital Construction has been very flexible with the school's needs.
What's next?
While construction on the Campus Center continues, Bailey and his staff are now focusing on some other aspects of getting the building operational by the summer of 2010. These other aspects include:
- Looking for furniture
- development/fundraising efforts
- determining operational procedures
- gathering an art collection to be displayed
Click here for a short slideshow of exterior models of the Campus Center.